This method statement comprise the application of 3mm thick cold applied reflectorized road marking paint on either sides , center and Pedestrian Crossings of the road using approved road marking material on existing road.
The following safety measures including traffic management will be taken
| No# | Machinery & Equipments | Qty | Remarks |
| 01 | High Pressure Cleaning Machines | 01 | Cleaning the Surface |
| 02 | Power Sweeper | 06 | Cleaning the Surface |
| 03 | Screed Type Road Marking Machines | 10 | Painting of Road |
| 04 | Crew Cab Trucks | 06 | To Transport Labor and Machinery |
| 05 | Water Bouser | 01 | Washing of the Road |
| 06 | Lighting Generator Towers | 04 | Working under Night Time |
| No# | Job Title | Qty | Remarks |
| 01 | Technical Officer | 01 | Arrangement of Work |
| 02 | Supervisor | 01 | Setting Out and Supervision |
| 03 | Pre Heater Operator | 01 | Controlling the temperature |
| 04 | Machine Operator | 01 | Road Marking |
| 05 | Guide Lines Marking | 02 | Marking the Guide Lines |
| 06 | Labors | 06 | Cleaning and carry out the process |
| 07 | Flag Man | 02 | Control the Traffic |
The work will be carried out as per the instructions and guide lines given by the Engineer.
As per the project quality assurance system, work will be carried out